On June 26, 2023, the Shanghai Lingang New City East Port Area Public Wharf Phase II project, undertaken by the Third Navigation Bureau, completed the pile foundation sinking operation of the approach bridge, creating a prerequisite for the smooth completion of the dock construction task.
![Shanghai Lingang Donggang Port Phase II Project Completed Pier Approach Bridge Pile Foundation Construction Approach Bridge | Pier | Project](https://a5qu.com/upload/images/889366ca5d6f58ff6564656b99a82b37.jpg)
This project is located on the west side of the Phase I project in Donggang District, Lingang New City, Shanghai. It is situated between the existing Luchao Port Ferry Terminal and the Shanghai Electric Heavy Cargo Terminal. The sea area is approximately 558000 square meters.
![Shanghai Lingang Donggang Port Phase II Project Completed Pier Approach Bridge Pile Foundation Construction Approach Bridge | Pier | Project](https://a5qu.com/upload/images/6cbbbae93fde5939b3b31e8eb9203951.jpg)
The main construction content and scale of the project are: building a new dock, setting up two 70000 ton roll on/roll off berths, and constructing a new approach bridge; Synchronize the implementation of port dredging, collision prevention facilities, electrical and other supporting projects.
![Shanghai Lingang Donggang Port Phase II Project Completed Pier Approach Bridge Pile Foundation Construction Approach Bridge | Pier | Project](https://a5qu.com/upload/images/ca34e16fa1c850e868a386cbb95807d6.jpg)
Zhu Jun, the person in charge of the Phase II project of the Lingang Port of China Communications Third Navigation Bureau, introduced that after the completion of this project, it will accelerate the integrated development of "production, transportation, and sales" of domestic automobile brands in China, help Shanghai build a logistics center for multimodal transportation commodity vehicles in the Yangtze River Delta, and provide strong support for the export of Chinese automobile brands overseas.