13 key projects in the urban area of Mentougou, Beijing have resumed work on foundation pits | Problems | Resumption of work
CCTV news: Affected by the rainstorm, key construction projects in Mentougou, Beijing, went into a shutdown state on July 29. Recently, with the recovery of production and life in Mentougou urban area, 13 key projects that had been suspended due to rainstorm have been resumed.
The reporter saw at the construction site of the new construction project of Yuyuan Primary School in Mentougou District that the project is currently in the underground main structure construction stage, with a deep foundation pit covering an area of over 4500 square meters. During the previous rainfall process, the accumulated water in the deep foundation pit reached a depth of 1.5 meters, and 16 pumping pumps were equipped to rush to discharge the accumulated water. At present, the accumulated water has been drained, and more than a hundred workers are carrying out operations such as binding steel bars on the foundation slab.
Wang Wei, Executive Manager of the New Construction Project at Yuyuan Primary School: We mainly conducted self inspections on key areas such as tower crane foundations, verticality, safety monitoring, and third-party monitoring. After conducting a self inspection and confirming that there were no issues, we invited experts from the foundation pit verification team to conduct a safety verification of the entire foundation pit and its verticality. With no issues found, work officially resumed on August 9th.
It is understood that during the summer vacation, many primary and secondary schools in the Mentougou urban area are renovating their playgrounds and other facilities. Currently, various renovation projects are rushing to complete the construction period to ensure that the new semester's teaching work is carried out as scheduled.
![13 key projects in the urban area of Mentougou, Beijing have resumed work on foundation pits | Problems | Resumption of work](https://a5qu.com/upload/images/b0d9dad312eb57297fb70e9610e67a72.png)
Gu Wenrui, Executive Manager of the Plastic Playground Renovation Project at Dayu Middle School Branch, also conducted a comprehensive safety inspection of the construction site as soon as possible, checking for any damage to the electrical system and equipment malfunctions. After testing, there are no issues with the corresponding products. We will officially resume work and production, ensuring normal delivery before August 18th.
The reporter learned from the Coordination Service Center for Major Construction Projects in Mentougou District that currently, 13 key projects in Mentougou urban area, including the construction of Yuyuan Primary School and Mentougou Archives, have passed comprehensive inspections and met the requirements for resumption of work.